- Advanced systems for utilizing waste heat from technological processes have been implemented using heat exchangers (economizers), resulting in reduced energy losses and optimized heat consumption.
The energy renovation project of the industrial building Color Emajl in Požega focuses on improving energy efficiency by replacing the existing heating system and integrating waste heat from production processes. The goal of the project was to enhance the energy efficiency of the facility, which includes a fireplace production hall, a section for the production of chimney pipes, and a storage area for semi-finished products.
Key Points
Investor
COLOR EMAJL D.O.O
Location
Požega
Capacity
786 kW (gas absorption heat pumps), 270 kW (utilization of waste heat from technological processes), 1046 kW (gas burners for technological processes)
About the project
High Energy Efficiency
Preparation of Hot Water
Improved Heat Distribution System
Safety and Durability
Environmental and Safety Measures
An Integrated PV Power Plant with a capacity of 33 kW has been installed on the roof of OFFSET PRINTING. This innovative installation, featuring 73 photovoltaic modules, harnesses the power of the ...